Contract No: HK/2009/05 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- june 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
7 July 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.14 Summary of Water Quality Monitoring Exceedances
in Reporting Month
Table 5.15 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.16 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.19 Details of Type I Marine Sediment
Disposal for Contract no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality
Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality
Monitoring Results and Graphical Presentations
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Concrete Block; and
¡P
Installation of
Caisson Seawall
¡P
Reclamation
works of HKCEC water Channel;
¡P
Assembly of
jack-up barge at Tsim Sha Tsui;
¡P
Installation of
sheet pile water channel at Dome Promenade;
¡P
Removal of rock
armours within the HKCEC Water Channel;
¡P
Installation of
cross-harbour water mains nos. B2 & As;
¡P
Thrust block
construction for cross-harbour watermains nos. A1 & B1 was commenced on 7 Jun
2011 when the steel formwork was installed into its working position;
¡P
Trench excavations
for proposed pipe laying works in Convention Avenue, VIP Drop-off Area;
¡P
Mainlaying works
at Zone B1-2 had been completed and the road reinstatement works;
¡P
Mainlaying works
at Zone B1-5;
¡P
Mainlaying works
at Zone A4-3A;
¡P
Backfilling
works for Temporary diversion of 2nos. DN900 cooling water discharge pipes of
Convention Plaza;
¡P
The fenced off
area at Zone B4-2 would be continued as a water tank establishment area for
cross harbour watermains installation until the original seawall had been
reinstated; and
¡P
Utility
diversion works for conflicting utilities at Salisbury Garden of Tsim Sha Tsui
¡P
Tseung Kwan O public fill sorting facility
¡P
Internal and external decoration for new public toilet;
¡P
FEHD pre-inspection of new public toilet;
¡P
Modification works for disable toilet;
¡P
Modification of hoarding and reinstatement works for public toilet opening
was carried out;
¡P
Basement structure and ground floor slab of passenger terminal building;
¡P
Modification of existing finger pier deck and tree pits;
¡P
Stripping interior fixing of existing ferry pier at Expo Drive East;
¡P
Erection of bamboo scaffolding;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Pipe jacking across Harbour Road;
¡P
Approximate
¡P
Excavation and lateral support for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Laying blinding layer for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Hacking H-pile head for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Excavation and lateral support at Wan Shing Street;
¡P
Dredging for submarine outfall pipe;
¡P
Approximate
¡P
Modification of ELS and formwork for top slab of DSD extension chamber;
¡P
Marine piling works for new ferry pier was ongoing. 43 out of 83 nos.
marine piles and
¡P
Excavation and lateral support for WSD & DSD receiving pits
¡P
Dredging of
odorous sediment at TS4;
¡P
Seawall block
construction at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
preparation work at TS1 and TPCWAE;
¡P
Grouting works
at Abutment A;
¡P
Night time
protection works at CHT; and
¡P
Trial trench
work at Hung Hing Road and POC
¡P
Erection of
Staging Platform; and
¡P
Marine Bored
Piling
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
3 |
1 |
1 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 &
HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
3 |
3 |
2 |
0 |
0 |
0 |
3 |
3 |
1 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Sheet Pilling;
and
¡P
Construction
& installation of Seawall Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Sheet pile
installation for a temporary water channel covering the existing cooling water
intake at Dome Promenade would be completed.
¡P
Removal of rock
armours within the HKCEC Water Channel would be continued.
¡P
Installation of
both silt screen type 1 & 3 at Tsim Sha Tsui would be completed.
Subsequently, installation of sheet piles near the proposed silt screen type 3
at Tsim Sha Tsui would be commenced.
¡P
Installation of
cross-harbour watermains nos. A3 & B3 and A4 & B4 would be completed.
¡P
Platform
erection fir crawler crane mobilization near the existing seawall at Salisbury Garden
would be continued and anticipated to be completed.
¡P
Works would be
continued at Convention Avenue, VIP Drop-off Area would be continued.
¡P
Excavation of
trial pot at Zone B5-1 and Zone b5-3 would be continued in order to determine
the suitable alignments for laying the proposed G1 ducts to and from the
existing HKCEC Phase 2 LV Switch room.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Modification
works for disable toilet;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining ferry pier;
¡P
Casting seawall
coping for Expo Drive East seawall modification;
¡P
Modification of
hoarding at Expo Drive East for public toilet opening.
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Lean concrete at
P7, P8 and P9 pump stations;
¡P
Hacking H-pile
head and cast the base slab at -5mPD for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street for WSD Salt Water Intake;
¡P
Pre-bored H-pile
at for WSD Salt Water Intake and Box Culvert N1 at WCR1 Area;
¡P
Dredging for
submarine outfall pipe; and
¡P
Connection
chamber at DSD Screening Plant
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Filling at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
construction at TS1 and TPCWAE;
¡P
Precautionary
works at Abutment A; and
¡P
Night time
protection works at CHT
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Erection of
Staging Platform; and
¡P
Disposal of Type
1 and Type 2 Marine Sediment for Pilling Works
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th May to 27th June
2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment
(EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001
and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Paul Yu |
9456 9819 |
|||
Operation Manager |
Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang |
9864 8615 |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan |
9312 2827 |
|||
Environmental Engineer |
Shelton Chan |
5395 5470 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658 3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|
|
|
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|
|
|
Environmental Manager |
Mr. Samuel Tsui |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Book Kin Man |
9193
8680 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Concrete Block; and
¡P
Installation of
Caisson Seawall
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Reclamation
works of HKCEC water Channel;
¡P
Assembly of
jack-up barge at Tsim Sha Tsui;
¡P
Installation of
sheet pile water channel at Dome Promenade;
¡P
Removal of rock
armours within the HKCEC Water Channel;
¡P
Installation of
cross-harbour water mains nos. B2 & As;
¡P
Thrust block
construction for cross-harbour watermains nos. A1 & B1 was commenced on 7 Jun
2011 when the steel formwork was installed into its working position;
¡P
Trench excavations
for proposed pipe laying works in Convention Avenue, VIP Drop-off Area;
¡P
Mainlaying works
at Zone B1-2 had been completed and the road reinstatement works;
¡P
Mainlaying works
at Zone B1-5;
¡P
Mainlaying works
at Zone A4-3A;
¡P
Backfilling
works for Temporary diversion of 2nos. DN900 cooling water discharge pipes of
Convention Plaza;
¡P
The fenced off
area at Zone B4-2 would be continued as a water tank establishment area for cross
harbour watermains installation until the original seawall had been reinstated;
and
¡P
Utility
diversion works for conflicting utilities at Salisbury Garden of Tsim Sha Tsui
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Tseung Kwan O
public fill sorting facility
¡P
Internal and
external decoration for new public toilet;
¡P
FEHD
pre-inspection of new public toilet;
¡P
Modification
works for disable toilet;
¡P
Modification of
hoarding and reinstatement works for public toilet opening was carried out;
¡P
Basement
structure and ground floor slab of passenger terminal building;
¡P
Modification of
existing finger pier deck and tree pits;
¡P
Stripping
interior fixing of existing ferry pier at Expo Drive East;
¡P
Erection of
bamboo scaffolding;
¡P
Trench
excavation and deck over works along Tonnochy Road;
¡P
Pipe jacking
across Harbour Road;
¡P
Approximate
¡P
Excavation and
lateral support for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Laying blinding
layer for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Hacking H-pile
head for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street;
¡P
Dredging for submarine
outfall pipe;
¡P
Approximate
¡P
Modification of
ELS and formwork for top slab of DSD extension chamber;
¡P
Marine piling
works for new ferry pier was ongoing. 43 out of 83 nos. marine piles; and
¡P
Excavation and
lateral support for WSD & DSD receiving pits
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Dredging of odorous sediment at TS4;
¡P
Seawall block construction at TS4;
¡P
Maintenance of navigation channel;
¡P
Diaphragm wall preparation work at TS1 and TPCWAE;
¡P
Grouting works at Abutment A;
¡P
Night time protection works at CHT; and
¡P
Trial trench work at Hung Hing Road and POC
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Erection of
Staging Platform; and
¡P
Marine Bored
Piling
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Sheet Pilling;
and
¡P
Construction
& installation of Seawall Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Sheet pile installation
for a temporary water channel covering the existing cooling water intake at
Dome Promenade would be completed.
¡P
Removal of rock
armours within the HKCEC Water Channel would be continued.
¡P
Installation of
both silt screen type 1 & 3 at Tsim Sha Tsui would be completed.
Subsequently, installation of sheet piles near the proposed silt screen type 3
at Tsim Sha Tsui would be commenced.
¡P
Installation of
cross-harbour watermains nos. A3 & B3 and A4 & B4 would be completed.
¡P
Platform
erection fir crawler crane mobilization near the existing seawall at Salisbury Garden
would be continued and anticipated to be completed.
¡P
Works would be
continued at Convention Avenue, VIP Drop-off Area would be continued.
¡P
Excavation of
trial pot at Zone B5-1 and Zone b5-3 would be continued in order to determine
the suitable alignments for laying the proposed G1 ducts to and from the
existing HKCEC Phase 2 LV Switch room.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Modification
works for disable toilet;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining ferry pier;
¡P
Casting seawall
coping for Expo Drive East seawall modification;
¡P
Modification of
hoarding at Expo Drive East for public toilet opening.
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Lean concrete at
P7, P8 and P9 pump stations;
¡P
Hacking H-pile
head and cast the base slab at -5mPD for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street for WSD Salt Water Intake;
¡P
Pre-bored H-pile
at for WSD Salt Water Intake and Box Culvert N1 at WCR1 Area;
¡P
Dredging for
submarine outfall pipe; and
¡P
Connection chamber
at DSD Screening Plant
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Filling at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
construction at TS1 and TPCWAE;
¡P
Precautionary
works at Abutment A; and
¡P
Night time
protection works at CHT
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Marine Bored
Piling;
¡P
Erection of
Staging Platform; and
¡P
Disposal of Type
1 and Type 2 Marine Sediment for Pilling Works
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
Table
3.2 Cumulative Summary of Valid Licences
and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-116 |
29 Dec 2010 |
31 Dec 2010 to 29 Jun 2011 |
Valid until 29 Jun 2011 |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/12-008 |
28 Apr 2011 |
30 Apr 2011 to 29 May 2011 |
Expired |
EP/MD/12-025 |
31 May 2011 |
1 Jun 2011 to 29 Jun 2011 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0045-10 |
21 Dec 2010 |
21 Dec 2010 to 20 Jun 2011 |
Expired |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1074-10 |
3 Dec 2010 |
09 Dec 2010 to 08 Jun 2011 |
Valid |
|
GS-RS0022-11 |
12 Jan 2011 |
23 Jan 2011 to 22 Jul 2011 |
Withdrawn |
|
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Valid |
|
GW-RS0311-11 |
1 Apr 2011 |
7 Apr 2011 to 6 Oct 2011 |
Withdrawn |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
6 May 2011 |
11 May 2011 to 10 Nov 2011 |
Valid |
|
GW-RS0450-11 |
20 May 2010 |
9 Jun 2010 to 8 Dec 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-021 |
20 May 2011 |
24 May 2011 to 23 Nov 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-164 |
6 Apr 2011 |
8 Apr to 7 May 2011 |
Expired |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong
Exhibition and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.5.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0037-10 |
3 Nov
2010 |
1 Dec 2010 to 31 May 2011 |
Expired |
|
PP-RS0046/10 |
24 Dec
2010 |
3 Jan to 31 May 2011 |
Expired |
|
PP-RS0011-11 |
27 April
2011 |
1 June 2011 to 30 Nov 2011 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1154-10 |
8 Dec 2010 |
8 Jan 2011 to 7 June 2011 |
Expired |
GW-RS0033-11 |
19 Jan 2011 |
01 Feb to 31 Jul
2011 |
Valid |
|
|
GW-RS0074-11 |
28 Jan 2011 |
1 Feb 2011 to 7 Jun 2011 |
Expired |
|
GW-RS0093-11 |
2 Feb 2011 |
17 Feb 2011 to 16 Jul 2011 |
Valid |
|
GW-RS0116-11 |
11 Feb 2011 |
15 Feb 2011 to 14 Jul 2011 |
Withdrawn |
|
GW-RS0225-11 |
17 Mar 2011 |
Withdrawn |
|
|
GW-RS0235-11 |
23 Mar 2011 |
31 Mar 2011 to 20 Jun 2011 |
Withdrawn |
|
GW-RS0280-11 |
30 Mar 2011 |
31 Mar 2011 to 30 Sep 2011 |
Valid |
|
GW-RS0310-11 |
1 April 2011 |
2 Apr 2011 to 14 July 2011 |
Withdrawn |
|
GW-RS0335-11 |
8 April 2011 |
11 Apr 2011 to 30 Sept 2011 |
Withdrawn |
|
GW-RS0343-11 |
11 April 2011 |
25 Apr 2011 to 10 Oct 2011 |
Valid |
|
GW-RS0369-11 |
21 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RS0377-11 |
27 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RE0311-11 |
4 May 2011 |
5 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RS0401-11 |
3 May 2011 |
18 May 2011 to 17 Nov 2011 |
Valid |
|
GW-RS0414-11 |
3 May 2011 |
9 May 2011 to 8 Nov 2011 |
Valid |
|
GW-RS0423-11 |
9 May 2011 |
22 May 2011 to 21 Nov 2011 |
Valid |
|
GW-RS0430-11 |
9 May 2011 |
16 May 2011 to 15 Nov 2011 |
Valid |
|
GW-RS0453-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0458-11 |
17 May 2011 |
21 May 2011 to 20 Nov 2011 |
Valid |
|
GW-RS0461-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0473-11 |
27 May 2011 |
01 Jun 2011 to 30 Nov 2011 |
Valid |
|
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011 to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011 to 12 Dec 2011 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 May 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 Apr 2016 |
Valid |
|
Billing Account under Waste
Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/10-093 |
25 Nov 2010 |
29 Nov 2010 to 28 May
2011 |
Expired |
|
EP/MD/12-012 |
6 May 2011 |
29 May 2011 to 28 Nov
2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-009 |
29 April 2011 |
10 May 2011 to 9 June 2011 |
Expired |
EP/MD/12-023 |
24 May 2011 |
10 June 2011 to 9 July 2011 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev. H |
15 Feb 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
|
Supplementary Information for
Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
Condition 2.12 (d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
19 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative
Screen Hoarding) |
11 May 2010 |
|
Landscape Plan (Control of
Night Time Lighting) |
2 June 2010 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0141-11 |
14 Feb 2011 |
15 Feb to 14 Aug 2011 |
Valid |
|
GW-RS0168-11 |
21 Feb 2011 |
24 Feb to 23 Aug 2011 |
Valid |
|
GW-RS0220-11 |
16 Mar 2011 |
16 Mar to 15 Sep 2011 |
Valid |
|
GW-RS0308-11 |
1 Apr 2011 |
4 Apr to 27 Sep 2011 |
Valid |
|
GW-RS0594-11 |
27 Jun 2011 |
29 Jun to 28 Dec 2011 |
Valid |
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Water Discharge Licence |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
|
WT00008905-2011 |
11 Apr 2011 |
11 Apr 2011 to 30 Apr 2016 |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping by
Vessel) |
7011761 |
28 Apr 2011 |
1 May 2011 to 30 Oct 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-120 |
17 Jan 2011 |
18 Jan 2011 to 17 Jul 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-017 |
19 May 2011 |
1 Jun 2011 to 30 Jun 2011 |
Valid until 30 Jun 2011 |
EP/MD/12-028 |
9 Jun 2011 |
1 Jul 2011 to 31 Jul 2011 |
To be valid since 1 Jul 2011 |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Works Schedule and Location
Plans |
27 Oct 2010 |
|
Amendment for Works Schedule
and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev 2 |
11 May 2011 |
Condition 2.9 |
Silt Screen Deployment Plan Rev3 |
15 Jun 2011 |
Condition 2.18 |
Amendment for Proposal for the
Removal of Odorous Sediment and Slime |
8 Mar 2011 |
Amendment for Noise Management
Plan |
27 Jan 2011 |
3.1.7.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix
3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0240-11 |
25 Mar 2011 |
7 Apr 2011 to 6 Oct 2011 |
Valid |
|
GW-RS0293-11 |
1 Apr 2011 |
6 Apr 2011 to 5 Oct 2011 |
Valid |
|
GW-RS0605-11 |
29 Jun
2011 |
13 Jul 2011 to 12 Jan 2012 |
To be valid since 13 Jul 2011 |
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-148 |
15 Mar 2011 |
22 Mar 2011 to 21 Sept 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-016 |
22 May 2011 |
22 May 2011 to 21 June 2011 |
Expired |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Works Schedule and Location
Plans |
11 March 2011 |
Condition 2.8 |
Silt Curtain Deployment Plan |
11 April 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
Real-time Noise Monitoring Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq (5 minutes) shall
be employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
CWB PRE
Site Office * |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE
Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6 - 1.7 m3 per
minute adjustable flow range;
¡P
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable of
providing a minimum exposed area of 406 cm2;
¡P
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped with a
shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped with a flow
recorder for continuous monitoring;
¡P
provided with a
peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able to hold and
seal the filter paper to the sampler housing at horizontal position;
¡P
easily
changeable filter; and
¡P
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS
accredited.
4.2.8.
An alternative non-HOKLAS
accredited laboratory was set-up for carrying out
the laboratory analysis, the laboratory equipment was approved by the ER
on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any
measurement performed by the laboratory was be demonstrated to
the satisfaction of the ER and IEC.
IEC shall regularly audit to the measurement performed by the laboratory
to ensure the accuracy of measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water
quality monitoring for dissolved oxygen (DO), suspended solid (SS) and
turbidity is therefore recommended to be carried out at selected WSD flushing
water intakes. The impact monitoring
should be carried out during the proposed dredging works to ensure the
compliance with the water quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V October) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 12 cooling water intakes along the seafront of the
Victoria Harbour. The proposed water quality monitoring stations of the Project
are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW21 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great Eagle
Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great Eagle
Centre (Western) |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table 4.5 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity should be measured in situ whereas SS should be
determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be capable of measuring:
¡P
a dissolved
oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a temperature of
0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare electrodes
and cables should be available for replacement where necessary. (e.g. YSI model
59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or
an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC power
source. It should have a
photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be
complete with a cable (e.g. Hach model 2100P or an approved similar
instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be handheld or
affixed to the bottom of the workboat, if the same vessel is to be used
throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO meter
shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when
necessary. Backup monitoring
equipment shall also be made available so that monitoring can proceed
uninterrupted even when some equipment is under maintenance, calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix 4.2.
Laboratory Measurement / Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water
samples of about 1L shall be collected at the monitoring stations for carrying
out the laboratory SS determination.
The SS determination work shall start within 24 hours after collection
of the water samples. The SS
determination shall follow APHA 19ed or equivalent methods subject to the
approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor
House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo
Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo
Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of
suspended solids and 24 hour monitoring of turbidity at the cooling water
intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The monitoring system include the
turbidity sensor and data logger which is capable of data capturing
at every 5 minutes. The data sahll be downloaded daily and compared with
the Action and Limit level determined during the baseline water qualtiy
monitoring at the cooling water intake locations.
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre; and
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.1.1.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
5.1.2.
Day time and evening period noise monitoring was
conducted at the City Garden and Victoria Centre in the reporting month.
5.1.3.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
No exceedance was recorded in the reporting month. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.4.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.5.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.6.
Four limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 2, 8, 14 and 24 June 2011 during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool.
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.1.7.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.8.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. No exceedance was recorded in reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
5.2.1.
No
construction activity with valid Construction Noise Permit was conducted during
night time period (2300 to 0700) in this reporting month.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.2.2.
The proposed division of real-time noise monitoring
stations are summarized in Table 5.4 below. Real time noise
monitoring for the filling works under contract no. HY/2009/11 was commenced on
5 October 2010.
Table 5.4 Real
Time Noise Monitoring Station for Contract no. HY/2009/11
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitefield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
5.2.3.
Real time noise monitoring results were reviewed
and no project-related Action and
Limit level exceedance were recorded in the reporting period. Details of real time noise monitoring results and graphical presentation
can be referred to Appendix 5.5 .
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.3.1.
The major construction activity of Contract no.
HY/2009/11 was filling works in the reporting month. Air monitoring had been
commenced on 11 August 2010. The proposed division of air monitoring stations
are summarized in Table 5.5 below.
Table 5.5 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.2.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix 5.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.3.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed division of air monitoring stations are summarized in Table
5.6 below. No exceedance was recorded in the reporting month.
Table 5.6 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.4.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.7 below. No
exceedance was recorded in the reporting month.
Table 5.7 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.3.5.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table
5.8 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.4.1.
Due
to the enforcement of amber rainstorm warning on 11 June 2011 at ebb
tide, water quality was considered substantially affected by urban
runoff, which cannot represent the normal impact condition of water quality and safety concerns on
working under adverse weather. Thus, the impact water monitoring on 11
June 2011 at ebb tide was cancelled.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.4.2.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.9 below:
Table 5.9 Water Monitoring Stations for Contract no. HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.3.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.10 below.
Table 5.10 Water
Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great
Eagle Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great
Eagle Centre (Western) |
835629.8 |
815889.2 |
Remarks:
The water monitoring
stations for the dredging works under Contract No. HK/2009/01 should also
include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.4.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.11 below.
Table 5.11 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.5.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.6.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.13 below.
Table 5.13 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.7.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011. One dissolved oxygen level at Ex-WPCWA-SE on 28
May 2011 during mid-ebb was exceeded.
5.4.8.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter between 7 and 28 June
2011,
daily monitoring of suspended solids and 24 hours monitoring of turbidity
at the cooling water intakes at C7
was be conducted. Due to no power supply from the Windsor House pumping House,
there was no monitoring data in a short period on 7, 12, 13, 14, 15 and 25 June
2011. No project-related exceedance was recorded in the daily SS monitoring and
24 hours turbidity monitoring.
5.4.9.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011 and no compliance checking for intake water monitoring at C6 was
undertaken in this reporting month.
5.4.10.
Water monitoring results measured in this reporting
period are reviewed and summarized.
Details of water quality monitoring results and graphical presentation
can be referred in Appendix 5.4.
Table 5.14 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
3 |
1 |
1 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
3 |
3 |
2 |
0 |
0 |
0 |
3 |
3 |
1 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.11.
Investigations were found that the exceedances are
not related to the Project works. The details of the recorded excedances can be
referred to the Section 6.3.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.5.1.
Non-inert C&D waste was disposed of in the
reporting month. The non-inert
C&D material is reported the unit in m3 in this reporting month.
The non-inert C&D material disposed in last reporting month was 4.875m3.
Details
of the waste flow table are summarized in Table 5.15.
Table
5.15 Details of
Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
146.25 |
151.125 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
N/A |
N/A |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
89,500 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
129,200 (Bulk Volume) |
East of Sha Chau |
5.5.2.
There was no marine sediment disposed and no
dredging work undertaken in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
5.5.3.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.16.
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
88.37 |
6,610.6 |
TKO137 |
Inert
C&D materials recycled, m3 |
0 |
0 |
N/A |
Non-inert
C&D materials disposed, m3 |
37.38 |
335.96 |
|
Non-inert
C&D materials recycled, kg |
0 |
78,088 |
N/A |
Chemical
waste disposed, kg |
1,200 |
3,730 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
6,659 (Bulk Volume) |
76,123.2 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
12,599 (Bulk Volume) |
East of Cha Chau |
5.5.4.
There were marine sediments Type 1 ¡V Open Sea
Disposal disposed in the reporting month. The maximum dredging rate in Cross
Harbour Water Main was 486m3 per day which was complied with the
recommended maximum dredging rate, 1500m3 per day listed in Table 2
of FEP-02/356/2009.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
5.5.5.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.17.
Table
5.17 Details of
Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
11,535 |
23,058 |
TKO137 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
24 |
128 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
1,104 |
2,115 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
4,004 (Bulk Volume) |
99,948 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
8,440 (Bulk Volume) |
90,994 (Bulk Volume) |
East of Sha Chau |
5.5.6.
There were marine sediments Type 1 ¡V Open Sea
Disposal disposed in the reporting month. The maximum dredging rate in submarine
sewage pipelines are 1,022m3 per day respectively, which is complied
with the recommended maximum dredging rate, 1500m3 per day listed in
Table 2 of FEP-03/356/2009.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
5.5.7.
Non- inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
3.5 |
Tuen Mun Area 38 |
|
58.7 |
58.7 |
TKO137 FB |
Inert
C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
Non-inert
C&D materials disposed, m3 |
27 |
66.4 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
NIL |
13,625 |
N/A |
Chemical
waste disposed, kg |
NIL |
NIL |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
2,010 |
16,518 |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
7,780 (Bulk Volume) |
139,582 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
0 (Bulk Volume) |
2,750 (Bulk Volume) |
East of Sha Chau |
5.5.8.
Due to the late notification of the Contractor on
the quantities of disposed Type I sediment, quantities from February 2011 to
this reporting month could only be included in this report. Details of the
quantities of disposed Type I sediment in Contract no. HY/2009/15 are
summarized in the Table 5.19. These quantities of disposed sediment
have been checked and verified by RSS for CWB. Contractor was reminded to
observe the dumping reporting time properly.
Table 5.19 Details of Type I Marine Sediment Disposal for Contract no. HY/2009/15
Waste Type |
Month |
Quantity this month, (Bulk Volume) |
Disposal / Dumping Grounds |
Feb 2011 |
6,070 |
South of Cheung Chau |
|
Mar 2011 |
7,465 |
South of Cheung Chau |
|
Apr 2011 |
973 |
South of Cheung Chau |
|
May 2011 |
0 |
South of Cheung Chau |
|
Jun 2011 |
2,010 |
South of Cheung Chau |
5.5.9.
In
the reporting month, there were marine sediment Type 1 ¡V Open Sea Disposal and Type 1
¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal
marine sediment disposed from the dredging works at TCBR.
The maximum dredging rate, 1,025m3 per day in the reporting month is
complied with the recommended maximum dredging rate as stipulated in FEP-04/356/2009
within the marine zones at TCBR.
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
5.5.10. No inert
and Non- inert C&D waste were disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for Contract no. HK/2010/06
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
NIL |
NIL |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
2,338 (Bulk Volume) |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
11,165 |
East Sha Chau |
5.5.11. Contractor
clarified that there was 4,674m3 Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined marine sediment disposed in May 2011. Thus, the cumulative
disposed Type 1 ¡V Open
Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined marine sediment was 11,165m3.
5.5.12. In the reporting month, there was no
dredging works at MTR tunnel crossing and no marine sediment disposed.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.1.1.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.1.2.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.3.
Four limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 2, 8, 14 and 24 June 2011
during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool. The construction works were complied with the conditions under
valid Construction Noise Permits during the measurement.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
6.1.4.
No exceedance was recorded in the reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.1.5.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.2.1.
No
project-related exceedance was recorded in the reporting month.
6.3.1.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.4.1.
Referring to the
exceedances shown in Table 5.9, one SS level was exceeded the
Action Level at Stations C8. Since there were numerous unknown outfalls from
the nearby coastal area closed to the cooling intakes C8, it causes the
potential for accumulation of pollutants near the intakes and may lead to
potential water quality deterioration at the seawater intake points. Besides,
muddy discharge from the outfalls near Oil Street was recorded in reporting
month.
6.4.2.
Major marine works were installations of caisson
seawall at NPR2E and reclamation work at NPR1 and NPR2W in this reporting
month. Proper condition of silt curtain was provided between the barge and the
seawall during the filling material transportation. The recorded SS exceedance
was considered as not project-related.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.4.3.
Referring
to exceedances recorded at WSD20 on 30 May and 1 June 2011 during mid-flood, no
exceedance was recorded in all stations in the vicinity of the filling works at
HKCEC1 and marine works for the Cross Harbour Water Mains. It concluded that
the exceedances were not related to Project works.
6.4.4.
For
the exceedances recorded at C2 on 15 June 2011, the daily inspection of silt
screen and removal of floating debris were provided by Contractor on that day.
The maintenance works of the silt curtain at West Bridge of HKCEC water channel
was conducted on that day morning. Additional sinkers were installed to enhance
the silt curtain effectiveness. According to the observation during the
monitoring, the deployed silt curtains along HKCEC water channel were in proper
condition and no muddy water dispersion was observed. Thus, it was considered not
project-related exceedances.
6.4.5.
An
Action Level SS exceedance was recorded at C4e on 30 May 2011. According to the
observation and recorded photos, the deployed silt curtains in HKCEC water channel
were in proper condition. The daily inspection of silt screen and removal of
floating debris were provided by Contractor on that day. Besides, geotextiles
were in good condition during their inspection. Thus, it was considered not
project-related exceedances.
6.4.6.
Exceedances
of turbidity and/or SS level at C3 were recorded on 28 and 30 May, 1, 7 and 13
June 2011. Investigation found that the turbidity levels outside the silt
screen on 28 May, 1, 7 and 13 June 2011 were well below the Action Level while
turbidity exceedances were recorded inside the silt screen. According to the
observation during the monitoring and daily inspection report, the deployed
silt screen and silt curtains along HKCEC water channel were in proper
condition. Recorded exceedances on these days might be caused by trapping of unknown
debris inside the silt screen.
6.4.7.
The
turbidity exceedance was recorded on 30 May 2011 while the turbidity level
outside the silt screen was slightly higher than the Action Level. Fine
particles were observed inside the silt screen during water quality monitoring.
According to the observation and recorded photos, the deployed silt curtains at
HKCEC water channel were in proper condition. The daily inspection of silt
screen and removal of floating debris were provided by Contractor on that day.
Geotextiles were in good condition during their inspection. The exceedances
were considered in related to accumulation of wastewater and debris from the
discharge pipe inside the silt screen and not project related exceedances.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.8.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
6.4.9.
There
was one DO level at ex- WPCWA SE exceeded the Action Level on 28 May 2011 in
the Enhanced DO monitoring. In view that no marine activities were undertaken
and no odour nuisance was noted during monitoring, the DO exceedance was
considered not related to the Project.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.10. No
exceedance was recorded in the reporting month.
6.4.11. Summary
for notification of exceedances can be referred to Appendix 6.2.
6.5.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.6.1.
To follow-up on the exceedances at C3 in the last
reporting month, a discharge
pipe for HKCEC located in between the C3 intake inlets and inside the silt
screen was diverted out of the silt screen and completed on 5 June 2011. Besides,
a bund between the eastern and western of the HKCEC water channel was formatted
on 2 June 2011 as an enhance mitigation measure to minimize the potential water
quality impact from the tidal effect.
6.6.2.
The implementation of the recommended mitigation
measures would be continuously followed-up and reported in the next reporting
period.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
From the Monthly EM&A report (May 2011) of
Central Reclamation Phase III (CRIII) the key works in June 2011 are as
follows:
¡P
Type A filling
in FRAW and FRAE above +2.5mPD;
¡P
General filling
works above +2.5mPD in IRAE;
¡P
Surcharging in
FRAW and FRAE;
¡P
Construction of
cantilever slab at caisson;
¡P
Construction of
storm and foul drainage and gullies in hinterlands for Road P2 and Road D9;
¡P
Construction of
GPO boundary wall;
¡P
Construction of
PLA boundary wall and entrance;
¡P
Construction of
Promenade enhancement works;
¡P
Construction of
buildings at PLA berth;
¡P
Road P2
Underpass ramp structures;
¡P
Precasting for
retaining wall (offsite);
¡P
Installation of
cooling mains discharge pipes in FRAE and FRAW;
¡P
Construction of
CWB structure;
¡P
Backfilling of
CWB structure;
¡P
Importation of
fill material; and
¡P
Strengthening of
Man Yiu Street Footbridge
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones under
Wan Chai Development Phase II were the filling works at NPR1, NPR2E, NPR2W, WCR1,
HKCEC1, TPCWAE and TCBR1E, dredging at TCBR1W, Submarine sewage pipeline and Cross
Harbour Water Mains, and marine works at MTR Tunnel Crossing in the reporting
month. The major environmental impact was water quality impact at North Point,
Causeway Bay and Wan Chai.
7.0.4.
The major environmental impacts generated from the
filling work at Central Reclamation Phase III were only located along the coastline
of Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact from
the concurrent projects including Wan Chai Development Phase II and Central
Reclamation Phase III was insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/11, HK/2009/01, HK/2009/02,
HY/2009/15 and HK/2010/06. No non-conformance was identified during the site
audits.
8.0.2.
Four site inspections for Contract no. HY/2009/11
were carried out on 30 May, 7, 17, and 21 June 2011. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections
for Contract no. HY/2009/11
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110530_02 |
30-May-11 |
Idle
stockpile should be covered well. |
Providing the tarpaulin to cover the idling
stockpile |
Completion
as observed on 7-Jun-11 |
110607_01 |
7-Jun-11 |
Oil stain was found near the oil drum. Contractor
was reminded to clear it and provide the drip tray for the chemical
container. |
Providing the drip tray underneath the chemical container
|
Completion
as observed on 17-Jun-11 |
110607_02 |
7-Jun-11 |
Worn tarpaulin for slope protection was found at NPR1. It should be replaced for well protection. |
Replacement of a new tarpaulin on the stockpile
for the dust suppression |
Completion
as observed on 17-Jun-11 |
110617_01 |
17-Jun-11 |
Unknown silty water washed out from the open
channel at reclamation area. Contractor was reminded to check and ensure
surface runoff and wastewater from the site shall be treated before
discharge. |
Deployment of silt curtain at the open channel to
suppress the silty water washing out during the rainy weather. |
Completion
as observed on 21-Jun-11 |
110617_02 |
17-Jun-11 |
Stockpile
at reclamation near the waterfront shall be covered by tarpaulin
in order to prevent washing away during wet season |
Providing the tarpaulin on the stockpile |
Completion
as observed on 21-Jun-11 |
110621_01 |
21-Jun-11 |
Exposed slope at NPR2 shall be covered by
tarpaulin to prevent washing away during rainy day. |
Providing the tarpaulin on the stockpile |
Completion
as observed on 28-Jun-11 |
110621_02 |
21-Jun-11 |
Silt curtain at channel T shall be mounted tightly |
Mounting the silt curtain tightly |
Completion
as observed on 28-Jun-11 |
110621_03 |
21-Jun-11 |
Floating
refuse near oil street site office area shall be removed |
Removal of the floating refuse |
Completion
as observed on 28-Jun-11 |
8.0.3.
Four site inspections for Contract no. HK/2009/01
were carried out on 1, 8, 16 and 22 June 2011. The results of these inspections
and outcomes are summarized in Table 8.2.
Table
8.2 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110601_01 |
1-Jun-11 |
Two derrick barges along the west bridge were
observed with dark smoke emission. Continuous checking and regular
maintenance need to be implemented. |
Contractor provided the checking and maintenance
works to the derrick barges. |
Completion
as observed on 8-Jun-11. |
110601_02 |
1-Jun-11 |
Silt curtain at HKCEC shall be closed properly
after access. |
Properly closed the silt curtain at HKCEC |
Completion
as observed on 8-Jun-11. |
110608_01 |
8-Jun-11 |
Silt curtain at western bridge shall be enhanced
so as to avoid gap between the geotextile. Increasing frequency of checking
silt curtain is recommended. |
Maintenance work on the silt curtain and daily inspection
on the silt curtains were provided. |
Completion
as observed on 16-Jun-11. |
110608_02 |
8-Jun-11 |
Chemical waste storage cabinet shall be provided
at the barge. |
Providing the chemical waste storage cabinet at
barge |
Completion
as observed on 16-Jun-11. |
110608_03 |
8-Jun-11 |
The top cover for the conveyor belt shall be
enhanced. |
Enhanced the top cover of conveyor belt |
Completion
as observed on 16-Jun-11. |
110616_01 |
16-Jun-11 |
Floating refuse near water monitoring stations C2
and C3 shall be removed. |
Keeping to removal of floating refuse |
Completion
as observed on 22-Jun-11. |
110616_02 |
16-Jun-11 |
Silt curtain for the leveling works at Cross
Harbour Water Main shall be weight down. |
Repaired and weighted-down the silt curtain |
Completion
as observed on 22-Jun-11. |
110616_03 |
16-Jun-11 |
Dark smoke emission was observed from air
compressor at north-bound of HKCEC water channel. Maintenance work shall be
provided to avoid dark smoke emission. |
Removed the air compressor offsite for the
maintenance works |
Completion
as observed on 22-Jun-11. |
110616_04 |
16-Jun-11 |
It was reminded to clear the filling material on
the walkway of the derrick barge after daily works. |
Removal of the filling material at the walkway of
the barge |
Completion
as observed on 22-Jun-11. |
110622_01 |
22-Jun-11 |
Part of silt curtain was sunk below the sea
level. Proper maintenance shall be provided after adverse weather. |
Maintenance the silt curtain in proper condition |
Completion
as observed on 29-Jun-11. |
8.0.4.
Four site inspections for Contract no. HK/2009/02
were carried out on 2, 9, 16 and 23 June 2011 during this reporting
period. The results of these
inspections and outcomes are summarized in Table 8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110602_01 |
2-Jun-11 |
Water
should be sprayed more frequently on the access road for dust control. |
Frequently spray water on the dry access and haul
road |
Completion
as observed on 09- Jun-11 |
110609_01 |
9-Jun-11 |
Uncovered
waste oil container without drip tray was located next to chemical waste
storage cabinet. Contractor shall place it properly and dispose it
regularly by register collector. |
Storage of the chemical in the cabinet and disposal
the chemical waste by register collector |
Completion
as observed on 16- Jun-11 |
110616_01 |
16-Jun-11 |
Drip
tray shall be provided to the oil container near the site entrance. |
Placed all oil container on drip tray |
Completion
as observed on 23- Jun-11 |
110623_01 |
23-Jun-11 |
Contractor
shall check and ensure that the wastewater at WSD pumping station shall be
treated before discharge. |
Contractor checked and confirmed wastewater was
treated by the sedimentation tank before discharge. |
Completion
as observed on 30- Jun-11 |
110623_02 |
23-Jun-11 |
Drip
tray shall be provided underneath the air compressor at ex-Pet Garden. |
Providing the drip tray underneath the air compressor |
Completion
as observed on 30- Jun-11 |
110623_03 |
23-Jun-11 |
Stockpile
of C&D material shall be covered after daily work. |
Leveling down the idling C&D material after daily
works |
Completion
as observed on 30- Jun-11 |
8.0.5.
Four site inspections for Contract no. HY/2009/15
were carried out on 31 May, 7, 14 and 21 June in reporting month. The results of these inspections and
outcomes are summarized in Table 8.4.
Table
8.4 Summary of
Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110531_01 |
31-May-11 |
Drip tray
shall be provided for chemical (Automatic transmission fluid) at TS1 |
Providing the drip tray underneath the chemical |
Completion
as observed on 7-Jun-11 |
110531_02 |
31-May-11 |
Accumulation of the stagnant water was found at the drip tray. Contractor was reminded to clear it with proper procedure to avoid land contamination. |
Removal of the stagnant water on the drip tray |
Completion
as observed on 7-Jun-11 |
110531_03 |
31-May-11 |
A gap was found at the
northern seawall block at TS1. Proper measure shall be
provided to avoid silty water washing
away during wet season. |
Gap filler was provided to minimize the gap at the
seawall block. |
Completion
as observed on 7-Jun-11 |
110531_04 |
31-May-11 |
Silty water was found
near the southern side of sea wall block, which
might
be caused by the runoff from the wheel washing at
resting area (protion7). |
Sand bags were provided to avoid water run-off to
the sea |
Completion
as observed on 7-Jun-11 |
110607_01 |
7-Jun-11 |
Mud was found
along Hing Fat Rd. The contractor was reminded to remove the mud and review the effectiveness of the vehicle wheel washing system. |
The mud was removed. Contractor washed the
vehicle wheel clearly before leaving the site. |
Completion
as observed on 14-Jun-11 |
110607_02 |
7-Jun-11 |
Impermeable barrier
shall be provided and fully deployed in case of any odour sediment dredging at
south-west corner of CWBTS. |
Impermeable
barrier will be provided if any odour sediment is dredged
and disposed. |
Completion
as observed on 14-Jun-11 |
110607_03 |
7-Jun-11 |
Silt
curtain at the Ex-PCWA shall be inspected and maintained. |
Keeping maintenance of the silt curtain at
ex-PCWA |
Completion
as observed on 14-Jun-11 |
110614_01 |
14-Jun-11 |
The contractor was reminded
to improve the wheel washing system at site entrance. Also, worn sandbags
shall be replaced for gully protection. Moreover, Improvement
work shall
be considered to avoid surface runoff flowing outside the site. |
Providing the sand bags for the gullies. |
Completion
as observed on 21-Jun-11 |
110614_02 |
14-Jun-11 |
The
plant shall be repaired to avoid dark smoke emission |
Providing maintenance works on the plant |
Completion
as observed on 21-Jun-11 |
110614_03 |
14-Jun-11 |
Oil spillage was
observed at Ex-PCWA reclamation area. The contaminated
soil on the bare ground shall be disposed as chemical waste. |
Removal the contaminated soil as chemical waste |
Completion
as observed on 21-Jun-11 |
110614_04 |
14-Jun-11 |
Silt curtain at the
entrance of Ex-PCWA shall be maintained. |
Maintaining the silt curtain at the entrance of
ex-PCWA. |
Completion
as observed on 28-Jun-11 |
110621_01 |
21-Jun-11 |
The deployed silt curtain at North-east of Ex-TPCWA
was found damage. The contractor was reminded
that silt curtain at North-east of Ex-TPCWA should be
maintained in a good condition prior to conduct any filling work at ex-TPCWA. |
Keeping maintenance of the silt curtain at Northeast exit of Ex-
TPCWA |
Completion
as observed on 28-Jun-11 |
110621_02 |
21-Jun-11 |
The
trees at yacht club shall be avoided any damage during excavation work at
Ex-TPCWA. |
The tree was avoided any damage during excavation
works |
Completion
as observed on 28-Jun-11 |
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110530_01 |
30-May-11 |
A chemical waste storage cabinet
shall be placed at site. |
Chemical
waste storage cabinet was provided at the flat-top barge. |
Completion as observed
on 7-June-11 |
110617_01 |
17-Jun-11 |
It was advised that additional
measure shall be provided to avoid oil leakage during the refilling fuel to
the generator |
A trip
will be provided when the refilling fuel to generator |
Completion as observed on 20-June-11 |
110627_01 |
27-Jun-11 |
Defect was found on the drip tray.
Contractor shall repair it to avoid oil spillage. |
Repairing
of the drip tray was provided |
Completion as observed on 27-June-11 |
9.0.1.
There
was one environmental complaint received on 9 June 2011 regarding an odour
nuisance suspected generating from the discharge point ¡V Channel T at Watson Road
in part of the site area was related to CWB under Contract no. HY/2009/11.
9.0.2.
During
the weekly site inspection on 7 and 17 June 2011, there was no any odour impact
detected in the site area. According to the site record, there was muddy water
discharged from the unknown source at upstream of Channel T during heavy
rainstorm. No any site surface runoff to the Channel T and out of site boundary
was observed in the inspection. In order to prevent muddy water washing out to
the water body under heavy rainstorm, a silt curtain was installed at the
outfall of the channel by Contractor. Besides, regular removal of refuse in the
channel has been conducted by Contractor. A further site investigation on 28
June 2011 revealed that no odour nuisance was detected at the upstream of the
Channel T and no source of odour nuisance was identified at site. As such, it
was concluded that the source of odour nuisance was not related to the Project
works.
9.0.3.
Although
no source of odour nuisance was identified at site, the muddy water and dirt from
the unknown source at upstream of Channel T may cause a potential smell during
low tide and low water flow. Contractor was reminded to remove the silt curtain
at the channel on non-rainy day so as to avoid the accumulation of the sediment
and dirt in the water channel.
9.0.4.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix 9.1.
9.0.5.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
11 |
June 2011 |
1 |
Project-to-Date |
12 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/11 |
¡P
Reclamation works; ¡P
Concreting; ¡P
Slotted panel fixing; ¡P
Drainage Construction works; ¡P
Outfall construction works; ¡P
Sheet Pilling; and ¡P
Construction & installation of Seawall Block |
¡P
To avoid concurrent noisy operation ¡P
To locate the plant and
equipments far away to the noise sensitive receivers ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly ¡P
Daily clearance of floating debris behind the silt screen |
HK/2009/01 |
¡P
Sheet pile installation for a temporary water channel
covering the existing cooling water intake at Dome Promenade would be
completed. ¡P
Removal of rock armours within the HKCEC Water Channel
would be continued. ¡P
Installation of both silt screen type 1 & 3 at Tsim
Sha Tsui would be completed. Subsequently, installation of sheet piles near
the proposed silt screen type 3 at Tsim Sha Tsui would be commenced. ¡P
Installation of cross-harbour watermains nos. A3 & B3
and A4 & B4 would be completed. ¡P
Platform erection fir crawler crane mobilization near the existing
seawall at Salisbury Garden would be continued and anticipated to be
completed. ¡P
Works would be continued at Convention Avenue, VIP
Drop-off Area would be continued. ¡P
Excavation of trial pot at Zone B5-1 and Zone b5-3 would
be continued in order to determine the suitable alignments for laying the
proposed G1 ducts to and from the existing HKCEC Phase 2 LV Switch room. |
¡P
To conform the installation and setting as in the silt
screen deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
To well maintain the mechanical
equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2009/02 |
¡P
Operating
Tseung Kwan O Public Fill Sorting Facility; ¡P
Modification
works for disable toilet; ¡P
Construction
of passenger terminal; ¡P
Demolition of
remaining ferry pier; ¡P
Casting
seawall coping for Expo Drive East seawall modification; ¡P
Modification
of hoarding at Expo Drive East for public toilet opening. ¡P
Trench
excavation and pipe laying works for cooling mains; ¡P
Trench
excavation and deck over at Tonnochy Road; ¡P
Lean concrete
at P7, P8 and P9 pump stations; ¡P
Hacking H-pile
head and cast the base slab at -5mPD for WSD Salt Water Pumping Station at
Wan Shing Street; ¡P
Excavation and
lateral support at Wan Shing Street for WSD Salt Water Intake; ¡P
Pre-bored
H-pile at for WSD Salt Water Intake and Box Culvert N1 at WCR1 Area; ¡P
Dredging for
submarine outfall pipe; and ¡P
Connection
chamber at DSD Screening Plant |
¡P
To cover the dusty material or stockpile by impervious
sheet; ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To well maintain the mechanical equipments / machineries
to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Movable noise barrier shall be
deployed for demolition works ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HY/2009/15 |
¡P
Seawall block
construction at TS4; ¡P
Filling at TS4; ¡P
Maintenance of
navigation channel; ¡P
Diaphragm wall
construction at TS1 and TPCWAE; ¡P
Precautionary
works at Abutment A; and ¡P
Night time
protection works at CHT |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2010/06 |
¡P
Marine Bored Piling; ¡P
Erection of Staging Platform; and ¡P
Disposal of Type 1 and Type 2 Marine Sediment for Pilling
Works |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |